So we’ve had our facelift SR for a month now and have been using the granny charger. I ordered a 7kw charger aged ago and have been waiting for the green light from the electricity board (in old money).
I received an email today saying they cannot give the go ahead as we need a service unloop. So far I’ve not heard back from the installer but it seems I need to wait for about three months for this to happen.
Has anyone been through this? Is it likely to cost me?
Thanks
Lee
I received an email today saying they cannot give the go ahead as we need a service unloop. So far I’ve not heard back from the installer but it seems I need to wait for about three months for this to happen.
Has anyone been through this? Is it likely to cost me?
Thanks
Lee